Under the Construction (Design and Management) Regulations 2015, welfare provision isn’t optional and it can’t be an afterthought. As a principal contractor, you’re legally required to have suitable welfare facilities in place before work begins, and to maintain them for the full duration of the project. CDM welfare requirements are detailed in Schedule 2 of the regulations and apply to every construction site where CDM 2015 is in force.
This checklist covers each requirement so you can verify your site against what the law demands before the HSE does.
What CDM 2015 Says About Welfare
Schedule 2 sets out the minimum facilities that must be provided on any construction site where CDM 2015 applies. In practice, that includes any project with more than one contractor, any project that lasts longer than 30 working days with more than 20 workers on site simultaneously, or any project exceeding 500 person-days.
The duty to provide welfare sits with the principal contractor on notifiable projects. On smaller projects involving a single contractor, that duty falls to the contractor directly. The HSE’s CDM guidance is clear: welfare facilities must be ready before any worker arrives on site.
National Site Standard welfare requirements are reshaping what good welfare provision looks like on UK construction sites. Authored by Construction for Women (CFW) and launched in the House of Lords in January 2026, the National Site Standard (NSS) is the UK’s first auditable framework for the conditions, facilities and behaviours that shape women’s experience on site. For contractors, clients and welfare providers, understanding what the standard actually requires, and how it sits alongside existing legal duties, is fast becoming a procurement question rather than a future one. Garic, a Considerate Constructors Scheme (CCS) registered organisation, has built its welfare offer around planning facilities before mobilisation for years, effectively meeting National Site Standard welfare requirements before they had a name.
CDM Welfare Requirements Checklist
1. Toilets and Sanitary Facilities
Toilets must be:
- Adequate in number for the maximum number of workers expected on site at any one time (see the ratios table below)
- Separated for men and women, unless each cubicle has a lockable door and access is from a shared area
- Adequately lit and ventilated
- Kept in a clean and orderly condition at all times
- Flushing where mains drainage is available; where it isn't, chemical alternatives must be provided and serviced regularly
Whatever your site setup, our site toilets and showers range has you covered, with self-contained, solar-powered and mains-connected options for both short-term and long-running projects.
2. Washing Facilities
Washing facilities must include:
- Wash basins large enough to allow face and hand washing
- Running hot and cold water, or warm water
- Soap and drying facilities such as paper towels or a hand dryer
- Clean and orderly conditions
Whatever your site setup, our site toilets and showers range has you covered, with self-contained, solar-powered and mains-connected options for both short-term and long-running projects.
3. Drinking Water
Drinking water is one of the more straightforward CDM welfare requirements to satisfy, but it’s still among those the HSE most often finds missing or poorly implemented on site. You must provide:
- A sufficient supply of wholesome drinking water
- Cups or drinking vessels where water is not from a drinking fountain
- Clear labelling to distinguish drinking water from any other water source on site
4. Changing Rooms, Drying Rooms and Lockers
Changing facilities are required wherever workers need to change into or out of special work clothing and can’t reasonably do so elsewhere. Facilities must include:
- Separate provision for men and women, or facilities that can be used separately
- Secure storage for clothing and personal belongings not worn during working hours
- Drying facilities where workers are regularly exposed to wet conditions
On outdoor or all-weather sites, a drying room is a practical necessity. Our static welfare units include models with integrated drying facilities, built for UK site conditions.
5. Rest Facilities
Rest areas must
- Be in a readily accessible location for all workers on site
- Include the means to prepare or obtain a hot drink and to heat food
- Provide protection from the weather
- Be separate from any area where harmful substances are used or stored
- Have seating with back support
On phased projects or multi-contractor sites, rest facilities must be available throughout. Sharing arrangements between contractors are acceptable provided they’re managed and the facilities remain adequate for the headcount at any given time.
Toilet-to-Worker Ratios
The number of toilets required on site depends on the maximum number of workers expected at any one time. The figures below are drawn from HSE guidance L153: Managing health, safety and welfare in construction.
Workers on site
Toilets Required
Urinals Required
Where a site has a significant proportion of female workers, replace urinals with additional toilet cubicles. Plan on at least one toilet per seven female workers on larger sites.
Who Is Responsible for CDM Welfare Compliance?
On any project with more than one contractor, the principal contractor is responsible for making sure welfare provision is in place and properly maintained across the whole site. That means:
- Making welfare facilities available to every worker on site, regardless of which contractor employs them
- Checking your provision keeps pace as worker numbers change throughout the project
- Making sure facilities are serviced regularly and kept clean
- Planning welfare unit locations before mobilisation, not after workers arrive
Our personal protection compliance service supports principal contractors with welfare auditing and ongoing checks, so you stay on top of your CDM welfare requirements from mobilisation through to completion.
Common Gaps Principal Contractors Miss
Even experienced principal contractors get CDM welfare requirements wrong in the same ways. Here are the issues the HSE most frequently picks up on inspection.
Underestimating peak headcount. Planning for average occupancy leaves sites short when multiple trades are working simultaneously. Base your calculations on the highest number of workers expected on site at any one time.
Facilities not ready at mobilisation. CDM requires welfare to be in place before work starts. Ordering units on day one of site is already non-compliant.
No provision for female workers. Sites that assume a predominantly male workforce and plan only urinals will fall short when that assumption proves wrong. Review your provision when subcontractor packages are awarded.
Poor placement. Welfare units that require a long walk across an active site, or that are inaccessible to workers in one part of a project, don’t meet the CDM requirement for facilities to be “readily accessible”. Plan locations based on where workers will actually be.
Infrequent servicing. Chemical toilets and welfare units must be serviced regularly to remain sanitary. Build a servicing schedule into your site programme from the start.
Planning Your CDM Welfare Provision from Day One
The best way to stay on top of CDM welfare requirements is to sort your provision before mobilisation, with accurate headcount projections and a site layout that puts facilities where your workers actually need them.
Our site design team will advise on the right solution for your project when you get in touch. Our welfare solutions range includes static and mobile welfare units that can be scaled as your project evolves, including eco and solar-powered options for sites with sustainability targets.
Whether you’re working in construction, infrastructure or utilities, our team will help you get the right welfare setup in place from day one.
Get in touch with our team to discuss your CDM welfare requirements.